Program Health at a Glance
Status as of Fri 11 Sep 2026 · Wk 4 · Phase 0Project Catalyst is in Week 4 of Phase 0 (Foundation) — the 12-week mobilization leg of a 36.5-month, $99.0M program running 17 Aug 2026 through 29 Aug 2029. Overall status is Green: the program is tracking to its approved schedule and cost baselines with no variances to report, which is expected this early in delivery. Foundation work is advancing on four parallel fronts — the AI Readiness Assessment, the AI Center-of-Excellence charter & governance framework, platform/cloud vendor selection, and early BRD-01 (Claims & Prior Authorization AI) requirements preparation ahead of the December design sign-off. The program's ten anticipated risks are logged on the RAIDD register as forward-looking items; none has yet materialized. Near-term focus: deliver the AI Readiness Assessment Report (25 Sep) and stand up the AI Governance Board and Enterprise Architecture Review Board so phase-gate governance is fully operational before Phase 1 design begins.
Top Program Risks anticipated · monitored
Budget Snapshot spend vs. baseline
Milestone Rail key program milestones · first year
Drill-Down: Scope, Risk & Quality
WBS Workstream Progress 7 elements · 64 work packages · budget-weighted
RAIDD Summary register at Wk 4
| Category | Count | Note |
|---|---|---|
| Risks | 10 | All anticipated · 0 realized |
| Assumptions | 6 | Baseline planning set |
| Issues | 0 | None open |
| Dependencies | 4 | 1 external (CMS-0057-F project) |
| Decisions | 3 | Logged in Phase 0 |
Phase-Gate Readiness
| Gate | Target | Status |
|---|---|---|
| G0 · Foundation | Nov 2026 | Prep |
| G1 · Requirements & Design | Feb 2027 | Not started |
| G2 · Build & Test | Jun 2027 | Not started |
Program Risk Heat Map inherent rating · anticipated register
How to read this: each of the program's ten anticipated risks is plotted by its inherent rating — likelihood (rows) against impact (columns), before mitigation. A cell's colour marks its severity zone; the risk IDs (e.g. RSK-01) show which risks sit where. None has yet been realized as an issue. Mitigation owners and controls for each are on the RAIDD Log.
Resource Utilization
current period · Phase 0 rampKey Roles — Phase 0 Loading foundation & governance ramp; delivery/validation ramp later by phase
Completion above is budget-weighted (EVM basis). The Resource-Loaded WBS reports schedule % complete (duration-weighted) for the same 11 Sep 2026 status date; the two measures differ by design.