Task Order Closeout Report — CDRL A010

Download Word

Final performance summary submitted to the COR and CO at the end of the Period of Performance, confirming delivery against the PWS and setting up formal contract closeout.

Performance Summary

Financial Reconciliation

LineAmount
Baseline Total Firm-Fixed Price (Base + Option)$3,550,000
Net Contract Modifications (11 mods, incl. P00011 scope addition)+$4,154,000
Final Adjusted Task Order Value$7,704,000

See the Task Order Budget for the baseline breakdown and the Contract Modification Log for the per-mod cost detail behind the +$4,154,000 adjustment, of which $4,040,000 is Mod P00011 alone.

Lessons Learned

Full detail — what happened, root cause, impact, and recommendation for each of these plus five more — is in the Lessons Learned Register.

Transition to Option Period

Stabilization support continues under the exercised Option Period, with reduced staffing and a shift from delivery cadence to sustainment/support cadence.