← Federal Suite 04 · Execution & Reporting

Contract Modification Detail

Download All 11 (Word)

Full SF-30-style modification document for each of the 11 contract mods logged on the Contract Modification Log — description, justification, cost/schedule impact, and the Contracting Officer's decision for each.

P00001

Add Independent Section 508 Auditor to CDRL Process

TypeAdministrative / Scope ClarificationRequested ByM. Whitcombe (COR)
Date SubmittedMay 22, 2026Date DecidedMay 29, 2026
Cost Impact+$28,000Schedule ImpactNone
CO DecisionApproved

Description: Adds an independent, third-party Section 508 auditor to the CDRL A004 (Section 508 Test Plan) and A006 (Section 508 / VPAT Compliance Test Report) review process, at the COR's direction, to provide an accessibility opinion independent of Acme Federal Systems' own P. Duvall.

Justification: FOPBA's accessibility program office requested an independent second opinion on Section 508 conformance for any citizen-facing federal system, standard practice for public-facing portals of this size.

P00002

Extend Legacy Data Read-Access Dependency Window

TypeSchedule AdjustmentRequested ByC. Tyrrell (Task Order PM)
Date SubmittedMay 27, 2026Date DecidedJun 3, 2026
Cost Impact$0Schedule Impact+15 days to Milestone Gate 1
CO DecisionApproved

Description: Extends the dependency window for read-only access to the legacy CareLink-style database by 15 days, after FOPBA's internal IT team was delayed granting credentials to Acme's data migration team.

Justification: Without extended access, the data migration and validation tasks tied to Milestone Gate 1 could not start on schedule through no fault of the contractor team.

P00003

Align CDRL A008 Monthly Status Report Format

TypeAdministrativeRequested ByM. Whitcombe (COR)
Date SubmittedMay 27, 2026Date DecidedJun 3, 2026
Cost Impact$0Schedule ImpactNone
CO DecisionApproved

Description: Updates the format of CDRL A008 (Monthly Status Report) to match FOPBA's newly adopted agency-wide status reporting template, replacing the original task-order-specific format.

Justification: FOPBA standardized status reporting across all active IDIQ task orders; no change to reporting content or frequency, only the template.

P00004

Add Multi-Factor Authentication to Citizen Portal Login

TypeScope Addition (Security)Requested ByT. Abernathy (ISSO)
Date SubmittedJun 1, 2026Date DecidedJun 8, 2026
Cost Impact+$45,000Schedule Impact+5 days to ATO gate
CO DecisionApproved

Description: Adds a Multi-Factor Authentication (MFA) requirement to the citizen-facing portal's login flow, following an updated OMB identity-assurance memo issued after contract award.

Justification: The updated OMB memo raises the required identity-assurance level for any federal system handling applicant PII — this Task Order's ATO could not be granted without it.

P00005

Extend ATO Authorization Bridge

TypeSchedule AdjustmentRequested ByT. Abernathy (ISSO)
Date SubmittedJun 4, 2026Date DecidedJun 11, 2026
Cost Impact$0Schedule Impact+30 days to go-live
CO DecisionApproved

Description: Extends the legacy BenefitConnect portal's interim (bridge) authorization by 30 days so the incumbent system remains lawfully operating throughout the modernization build. The bridge must not lapse before the replacement system receives its own ATO at Milestone Gate 1 (Dec 14, 2026); this mod aligns the bridge's expiry with the new system's authorization date rather than leaving a gap at go-live.

Justification: The legacy portal's existing authorization was scheduled to expire mid-build. Operating an unauthorized federal system carrying applicant PII is not permissible, so the Authorizing Official extended the bridge administratively. Identified during the Task Order's first security posture review and raised immediately rather than at expiry.

P00006

Add Automated Accessibility Regression Testing

TypeScope Addition (Section 508)Requested ByP. Duvall (508 Lead)
Date SubmittedJun 9, 2026Date DecidedJun 16, 2026
Cost Impact+$18,000Schedule ImpactNone
CO DecisionApproved

Description: Adds an automated accessibility regression-testing tool license to run alongside manual VPAT testing on every release, rather than manual testing alone.

Justification: Manual-only testing could not keep pace once the front-end development team grew to two developers shipping more frequent UI changes — automated regression catches accessibility defects between manual test passes.

P00007

Reduce Data Migration Tooling Scope

TypeCost DecreaseRequested ByH. Ibrahim (Back-End Developer)
Date SubmittedJun 12, 2026Date DecidedJun 26, 2026
Cost Impact-$12,000Schedule ImpactNone
CO DecisionApproved

Description: Reduces the planned Data Migration Tooling spend after the legacy vendor provided a cleaner, better-structured data export than originally scoped, requiring less custom transformation tooling.

Justification: Passing a genuine cost savings back to the government rather than retaining the original tooling budget for work that turned out to be unnecessary.

P00008

Add Disaster Recovery / COOP Testing

TypeScope AdditionRequested ByS. Vance (DevOps / Cloud Engineer)
Date SubmittedJun 17, 2026Date DecidedJul 1, 2026
Cost Impact+$35,000Schedule ImpactNone
CO DecisionApproved

Description: Adds a Disaster Recovery / Continuity of Operations (COOP) test to the Cloud Hosting line, verifying the portal can fail over to a secondary region within FOPBA's required recovery time objective.

Justification: COOP testing was implied but not explicitly priced in the original PWS; FOPBA's COR asked for it to be made explicit and billed rather than absorbed informally.

P00009

Correct Business Analyst Labor Category Title

TypeAdministrativeRequested ByA. Reyes (Contracting Officer)
Date SubmittedJun 17, 2026Date DecidedJul 1, 2026
Cost Impact$0Schedule ImpactNone
CO DecisionApproved

Description: Corrects J. Okonkwo's labor category title from "Business Analyst" to FOPBA's standard labor category taxonomy term, "Requirements Analyst II," to match the IDIQ's labor category schedule exactly.

Justification: A labor-category audit found the Task Order's invoicing used an informal title not present on the HSS-IDIQ labor category schedule — corrected for invoicing consistency, no change to role, rate, or duties.

P00010

Exercise Option Period

TypeOption ExerciseRequested ByA. Reyes (Contracting Officer)
Date SubmittedJun 22, 2026Date DecidedJul 2, 2026
Cost Impact$0 (pre-priced at award)Schedule Impact+6 months period of performance
CO DecisionApproved

Description: Formally exercises the Task Order's 6-month Option Period, pre-priced at contract award, extending the period of performance and continuing the delivery team's sustainment and Continuous ATO Monitoring support. The Option Period runs May 18, 2027 – Nov 17, 2027, immediately following the 12-month Base Period; exercising it in Month 2 fixes the period of performance at the full 18 months well ahead of the normal decision point.

Justification: Exercised early, in the fourth quarter of FY2026, rather than at the normal decision point near the end of the Base Period. The Contracting Officer made a written determination under FAR 17.207(c)–(d) that exercising the pre-priced option was the most advantageous method of fulfilling the requirement, price and other factors considered, and obligated available FY2026 funds against it ahead of the 30 September fiscal-year close. Two drivers: (1) the Option Period covers Continuous ATO Monitoring immediately following Milestone Gate 1, and a funding lapse there would leave an authorized production system without contracted monitoring support; (2) obligating in FY2026 protects the Task Order against a possible FY2027 continuing resolution. This invalidated assumption A-02 (“the Option Period will be exercised based on satisfactory Base Period performance”) — the decision was driven by appropriations timing, not by performance to date. The RAIDD Log records A-02 as not holding as written; performance was nonetheless satisfactory across all CDRL acceptances at the time of exercise.

P00011

Add Mobile-Responsive Redesign & Benefits-Eligibility Verification API Integration

TypeScope AdditionRequested ByR. Osei (Federal Business Owner / Sponsor)
Date SubmittedJun 22, 2026Date DecidedJul 10, 2026
Cost Impact+$4,040,000Schedule ImpactNone — absorbed within the existing 18-month period of performance
CO DecisionApproved

Description: Adds two new capabilities out of scope at contract award: (1) a mobile-responsive front-end redesign — the original portal was desktop-only, which FOPBA's own Section 508 program office flagged as a real accessibility gap for citizens using mobile devices; and (2) a real-time integration to the agency's Benefits-Eligibility Verification API, replacing a manual lookup step caseworkers previously performed by phone. Delivering both requires growing the delivery team from 13 to 35 people — additional front-end and back-end developers, a Data Migration Specialist for the new eligibility data source, a Security Engineer to review the new external API integration, expanded QA/accessibility testing capacity, a UX/Accessibility Designer, and proportional PM/BA/DevOps/documentation support. Full detail in the Resource Plan and Task Order Budget.

Justification: Both capabilities were identified during early Base Period requirements analysis as gaps in the original PWS scope, not staffing miscalculations against existing scope — the original 13-person team was correctly sized for the originally awarded scope. Funding this as a Contract Modification (rather than absorbing it against the existing $3,664,000 baseline) reflects that this is new deliverable scope requiring its own negotiated price, consistent with FAR change-order practice for out-of-scope work on a Firm-Fixed-Price Task Order.