← Stage-Gate NPD Suite Baselined Only to the Funded Horizon

Resource-Loaded WBS

Excel MS Project
Program timeline · status 16 Oct 2026Read the full story →
Harborline
Aug 2025
Cancelled
Gate 0
Feb 2026
Go
Stage 1
Business case
Gate 1
Apr 2026
Recycled
Gate 1
Jun 2026
Go w/ conditions
Stage 2
Development
You are here
Gate 2
Apr 2027
Gate 3
Oct 2027
Gate 4
Feb 2028
Launch
Mar 2028
Gate 5
Sep 2028

Lighthouse Financial Services Company — The work breakdown structure for Beacon Index Advantage, derived from the 90-person roster and split by authorization state. Status as at 16 October 2026.

36%
Of program hours baselined
53,184
Hours baselined (Stages 1–2)
93,256
Hours in unfunded stages
25
Work packages

The filled portion is what can be baselined. The remainder is planned, not authorized.

Contents
  1. Why This WBS Stops Where It Does
  2. The Structure
  3. Work Package × Team Allocation
  4. What the Loading Shows
  5. Reconciliation
  6. Files

1. Why This WBS Stops Where It Does

A resource-loaded WBS normally covers the whole program: every package decomposed, every activity staffed, every hour costed through to the end. This one deliberately does not.

Stages 3 and 4 are not funded. Decomposing them to activity level and publishing a resource load would present a staffing commitment against $11,780,000 the Board has not released and may decline to release. It is the same objection that keeps a full-program earned value baseline off the Dashboard (Decision D-10) — a plan against unapproved money is a forecast wearing a baseline's clothing.
StagesStateTreatment in this WBS
1 & 2FundedBaselined — decomposed to work-package level, resource-loaded from the roster, costed.
3 & 4Not releasedPlanning envelope — work packages named so the shape of the work is visible, stage-level hours shown as an intention, not loaded and not baselined.
Only 36% of the program's hours can be baselined at all. That is not a gap in the planning — it is an accurate statement of how much of this program has been authorized. A WBS showing 100% loaded would be the less honest document, and the harder one to defend at a gate.

2. The Structure

StageWBSWork packageHoursCostAssigned resources (hours)
1Stage 1 — Business Case & Feasibility15,701$2,215,829Closed
1.1Concept definition & product structure2,198$310,196PROD 1,493 · PMO 503 · ACT-P 115 · DIST 45 · MKTG 42
1.2Preliminary pricing & capital assessment4,082$576,079ACT-P 1,693 · PMO 1,246 · FIN 595 · INV 548
1.3Regulatory route assessment2,041$288,039LEGAL 846 · PROD 451 · PMO 380 · REG 364
1.4Platform & illustration feasibility2,669$376,667IT-PLT 1,634 · IT-ILL 418 · OPS 275 · DATA 259 · PMO 83
1.5Distribution appetite assessment1,570$221,569PROD 518 · PMO 436 · DIST 394 · MKTG 222
1.6Gate 1 package preparation1,884$265,883PMO 1,192 · PROD 237 · BOARD 189 · LEGAL 147 · ACT-P 45 · REG 38 · DIST 36
1.7Gate 1 recycle remediation1,257$177,396PMO 757 · ACT-P 228 · BOARD 121 · DIST 91 · FIN 60
2Stage 2 — Development37,483$4,691,986In progress
2.1Product specification & contract forms5,997$750,683PROD 3,160 · DIST 738 · REG 664 · LEGAL 589 · PMO 582 · MKTG 264
2.2Pricing basis & external peer review5,248$656,926ACT-P 3,681 · ACT-V 642 · PMO 562 · FIN 363
2.3Platform configuration — Cordelane WP-18,996$1,126,087IT-PLT 6,288 · OPS 1,403 · DATA 1,027 · PMO 278
2.4Illustration engine build — Brightpath5,622$703,742IT-ILL 3,724 · IT-PLT 630 · PROD 367 · ACT-P 367 · DATA 309 · PMO 168 · LEGAL 57
2.5Hedging design & ISDA onboarding4,123$516,102INV 1,291 · PMO 1,197 · FIN 773 · ACT-V 457 · LEGAL 405
2.6Reinsurance structuring — Halverson Re2,249$281,522ACT-V 891 · PMO 586 · LEGAL 395 · FIN 377
2.7Filing preparation3,373$422,220REG 1,867 · PROD 593 · PMO 544 · LEGAL 369
2.8Gate 2 package preparation1,875$234,706PMO 680 · BOARD 310 · DIST 287 · OPS 284 · ACT-P 125 · PROD 123 · REG 66
3Stage 3 — Testing & Validation46,810 env.$5,644,649 env.Not released
3.1Master test executionNot loaded — stage unfunded
3.2Regulatory filing & response managementNot loaded — stage unfunded
3.3Illustration validationNot loaded — stage unfunded
3.4Operations process buildNot loaded — stage unfunded
3.5Gate 3 package preparationNot loaded — stage unfunded
4Stage 4 — Launch Readiness46,446 env.$5,427,536 env.Not released
4.1Distribution enablement & advisor trainingNot loaded — stage unfunded
4.2Operations readiness & cutoverNot loaded — stage unfunded
4.3Hedging go-live & shadow bookNot loaded — stage unfunded
4.4Launch readiness verificationNot loaded — stage unfunded
4.5Gate 4 package preparationNot loaded — stage unfunded

env. marks a planning envelope figure — the roster's intention for that stage, not an authorized baseline. Work packages inside those stages carry no hours because allocating them would imply a commitment that does not exist.

WBS 1.7 is the recycle. The Gate 1 remediation loop is a work package in its own right, carrying its own hours and its own cost, rather than being absorbed silently into 1.6. A WBS that hid the loop inside package preparation would make the program look like it went from concept to Gate 1 in a straight line.

3. Work Package × Team Allocation

This is the loading itself. Every column sums to its work package's hours; every row sums to that team's hours in the stage. Both margins are fixed independently — package hours come from the WBS split, team hours from the roster — so the matrix is solved rather than typed, and the generator refuses to write if either margin fails to tie.

Stage 1 — closed

Team1.11.21.31.41.51.61.7Total
Product Development PMO (PMO)5031,246380834361,1927574,597
Product Management & Design (PROD)1,4934515182372,699
Actuarial - Pricing & Product Development (ACT-P)1151,693452282,081
IT - Annuity Administration Platform (IT-PLT)1,6341,634
Legal & Compliance (LEGAL)846147993
Finance & Treasury (FIN)59560655
Distribution & Wholesaling (DIST)453943691566
Investments - ALM & Hedging (INV)548548
IT - Illustration & Quoting (IT-ILL)418418
Regulatory Filing & Contract Forms (REG)36438402
Gate Review Board (oversight only) (BOARD)189121310
Operations - New Business & Policyholder Services (OPS)275275
Marketing & Advisor Enablement (MKTG)42222264
Data, Reporting & Analytics (DATA)259259
Work package total2,1984,0822,0412,6691,5701,8841,25715,701

Stage 2 — in progress

Team2.12.22.32.42.52.62.72.8Total
IT - Annuity Administration Platform (IT-PLT)6,2886306,918
Product Development PMO (PMO)5825622781681,1975865446804,597
Product Management & Design (PROD)3,1603675931234,243
Actuarial - Pricing & Product Development (ACT-P)3,6813671254,173
IT - Illustration & Quoting (IT-ILL)3,7243,724
Regulatory Filing & Contract Forms (REG)6641,867662,597
Actuarial - Valuation & Financial Reporting (ACT-V)6424578911,990
Legal & Compliance (LEGAL)589574053953691,815
Operations - New Business & Policyholder Services (OPS)1,4032841,687
Finance & Treasury (FIN)3637733771,513
Data, Reporting & Analytics (DATA)1,0273091,336
Investments - ALM & Hedging (INV)1,2911,291
Distribution & Wholesaling (DIST)7382871,025
Gate Review Board (oversight only) (BOARD)310310
Marketing & Advisor Enablement (MKTG)264264
Work package total5,9975,2488,9965,6224,1232,2493,3731,87537,483
There is no Stage 3 or Stage 4 matrix, and that is the point of §1. Those stages have hours in the roster's planning envelope but no released funding, so allocating named teams to named work packages would publish a staffing commitment against money the Board has not approved.

4. What the Loading Shows

  1. The program's effort peak sits entirely inside the unfunded stages. Stages 3 and 4 carry 93,256 hours against 53,184 in Stages 1 and 2 — roughly two thirds of the work is planned beyond the funded horizon. That is normal for stage-gate and worth stating plainly, because it means the largest resourcing commitment the carrier will make has not yet been made.
  2. Stage 1 is the smallest stage and produced the largest governance event. 15,701 hours — 11% of the program — and it is where the recycle happened. Cheap stages are where gates earn their cost.
  3. Assumption A-08 is the exposure this table makes visible. Stage 3 and 4 loading assumes the same actuarial and IT people are available in 2027, and the program holds no claim on any of them. The hours are real planning; the availability is an assumption.

5. Reconciliation

CheckThis WBSSourceStatus
Total hours146,440146,440Ties
Total labor cost$17,980,000$17,980,000Ties
Stage 1 work packages15,70115,701Ties
Stage 2 work packages37,48337,483Ties

The generator refuses to write any of the three files if these fail. Hours and cost are derived from lighthouse-roster.csv, the same source the Resource Plan and Org Chart read, so the four documents cannot disagree about who is on the program or for how long.

6. Files

FileContents
program-wbs.xlsxThe full structure, stage summary and per-team loading, with the reconciliation as live formulas.
program-wbs.xmlMS Project XML — tasks with WBS codes and outline levels, calendar, the 15 teams as resources, and assignments for the baselined stages only. Stages 3 and 4 import as unstaffed summary tasks, which is the correct representation of unfunded work.

Maintained by C. Tyrrell, NPD Program Manager and Chair of the Gate Review Board, with K. Iyer, PMO Lead. Related: Resource Plan · Program Budget · Program Dashboard · Methodology Guide §5.