← PM Suite Project Closeout Report

Enrollment & Claims Platform Modernization

Download Word

Project Closeout Report

Enrollment & Claims Platform Modernization — ACME Company

Report Date05 Nov 2027Prepared following formal Closeout (02 Nov 2027)

1. Purpose & Overview

This report formally closes the Enrollment & Claims Platform Modernization program, following the Executive Sponsor and Steering Committee's Go-Live authorization (24 Aug 2027) and completion of the post-implementation warranty period. It evaluates the program's success against the objectives set in the Project Charter, summarizes final cost and schedule performance, and hands over open items to operations.

2. Performance Against Baseline

Final Cost
$7,210,000
Cost Performance Index
0.979
Schedule Performance
On Baseline
MetricBaselineActualResult
Total Cost$7,062,000$7,210,000 (+2.1%)Within contingency reserve
Go-Live Date24 Aug 202724 Aug 2027On schedule
Data Conversion Accuracy≥99.5%99.6%Met
UAT Pass Rate (first cycle)≥90%93%Met
Critical/High Security Findings at Go-Live00Met
Training Completion≥95%97%Met
Hypercare Severity-1 Incidents≤21Met

R-001 (historical claims data quality — the program's highest-rated risk at Charter approval) was successfully managed through early profiling and automated cleansing; the reserved third Dry Run cycle (D-002) was not ultimately needed.

3. Benefits Realization

Per the Cost-Benefit Analysis, benefit realization ramps over the first two years post-Go-Live (50% Year 1, 80% Year 2, 100% from Year 3). As of this report, the program is one week past Go-Live — benefit tracking has not yet begun and is not expected to show meaningful results until the first full quarter of operation. The PMO will monitor realization against the CBA's model and report to the Steering Committee quarterly for the first two years.

4. Deliverables & Acceptance

DeliverableAcceptance
Platform UpgradeAccepted — validated by System Upgrade Lead, signed off by Steering Committee (05 Jan 2027)
Data Conversion (member/policy, provider/producer, historical claims)Accepted — 99.6% record-match accuracy, signed off by Steering Committee (16 Mar 2027)
Six System Integrations (Billing, Underwriting, Claims Admin, Commission Mgmt, Data Warehouse/Reporting, Payment Processing)Accepted — all passed integration testing (11 May 2027)
Security, Performance & DR TestingAccepted — zero open Critical/High findings at Go-Live
SOX Compliance TestingAccepted — signed off by Chief Compliance Officer prior to Go-Live

5. Outstanding Items & Follow-on Actions

ItemOwnerTarget
Full legacy system decommissioning (DEP-005) — warranty period complete, final teardown in progressM. Alvarez30 days post-Closeout

All other risks, issues, and dependencies tracked in the RAIDD Log are closed as of this report.

6. Team Performance

The program was delivered by a 20-person matrixed team spanning Core Delivery, Integration Development, Quality Assurance, Change & Training, Compliance & Governance, and Vendor/Procurement functions (see the Organizational Chart). The Program Manager recognizes the team's effective early response to the R-001 data quality risk and the successful dual-shore QA model adopted mid-program as particular contributors to the program's on-baseline finish.

7. Lessons Learned Summary

Eight lessons were formally captured across data quality, governance, compliance, resourcing, vendor management, risk management, change management, and schedule management. Full detail, including specific recommendations for future programs, is in the standalone Lessons Learned Register.

8. Administrative Closure

9. Approval

This report formally closes the Enrollment & Claims Platform Modernization program.

 

G. Whitfield, Executive Sponsor
 

C. Tyrrell, Program Manager