← PM Suite RAIDD Log

Enrollment & Claims Platform Modernization

Download Excel

RAIDD = Risks, Assumptions, Issues, Dependencies, Decisions — the single log referenced throughout the PM Plan, Governance Model, Dashboard, and Steering Committee Deck. Risk authority (who can accept, escalate, or fund a response) is defined in Project Governance Model §10 — this page is the record of what those risks, issues, and decisions actually are.

6
Risks
5
Assumptions
5
Issues
5
Dependencies
4
Decisions
Risks

Risk Register

IDRiskScoreOwnerStatusResponse
R-001Historical claims data quality issues could extend Data Conversion if root-cause cleansing proves insufficient9 (High/High)T. McCormickWatchEarly profiling & automated cleansing rules underway ahead of Dry Run 2; contingency reserved for a third Dry Run (see Decisions)
R-002Offshore/onshore QA coordination gaps could reduce testing throughput4 (Medium/Medium)R. WhitfieldMitigatedDaily overlap-hour standup in place; Offshore QA Coordination Lead role added (CR-007)
R-003Vendor SOW negotiation delay could push back Environment Provisioning6 (Medium/High)W. DonnellyMitigatedBackup vendor pre-qualified as contingency
R-004Mid-program state insurance filing/reporting requirement change could add unplanned compliance scope3 (Low/Medium)N. SharmaMonitoringCompliance monitoring regulatory calendar; no action needed at this time
R-005Legacy system documentation gaps could complicate Decommissioning planning3 (Low/Medium)M. AlvarezMonitoringKnowledge transfer sessions scheduled ahead of Phase 6
R-006Key resource attrition (particularly Solution Architect capacity) could disrupt technical continuity4 (Low/High)C. TyrrellMitigatedCross-training as contingency, not prevention
Assumptions

Assumptions

IDAssumptionOwner
A-001Existing network and security infrastructure is sufficient to support the upgraded platform without separate capital investmentC. Tyrrell
A-002Named resources are available at their planned allocation; no extended unplanned absences are assumedC. Tyrrell
A-003The platform vendor's proposed system upgrade approach will not require a change to the underlying database platformM. Alvarez
A-004The program must complete Go-Live prior to the start of the next open-enrollment periodC. Tyrrell
A-005Historical claims data, once cleansed, will not require additional legal/compliance review beyond what's already scopedN. Sharma
Issues

Issue Log

IDIssueOwnerStatusResolution
I-001Early data profiling revealed higher-than-expected duplicate member records in historical claims dataT. McCormickClosedAdditional de-duplication pass added to conversion pipeline
I-002Initial vendor-provided test environment lacked production-representative data volume, delaying early integration testingM. AlvarezClosedVendor provisioned an expanded test environment
I-003Intermittent VPN connectivity to the offshore QA environment affecting testing throughputP. SundaramOpenTracking resolution with internal IT; interim workaround in place
I-004Discrepancy identified between Commission Management integration spec and legacy calculation logicP. NovakClosedResolved via joint review with Business Data Owners
I-005External penetration test finding: staging environment TLS configurationM. AlvarezResolvedPatched and re-scanned clean
Dependencies

Dependency Log

IDDependencyOwnerStatus
DEP-001Data Warehouse/Reporting integration depends on Data Conversion Sign-off completing firstA. ReyesOn Track
DEP-002SOX compliance testing depends on Security & Penetration Testing completing firstG. FenwickOn Track
DEP-003Platform vendor SOW must finalize before Environment Provisioning can beginW. DonnellyAt Risk
DEP-004Training content development depends on final UAT-validated workflowsH. OseiOn Track
DEP-005Legacy System Decommissioning depends on the Warranty Support period completingM. AlvarezOn Track
Decisions

Decision Log

IDDecisionDecided ByDate
D-001Adopt a hybrid waterfall/agile methodology — waterfall for requirements & vendor selection, agile sprints for integration build, gated phases for testingSteering Committee04 Aug 2026
D-002Pre-approve contingency utilization of up to $150,000 for a third Data Conversion Dry Run cycle, should root-cause cleansing of R-001 prove insufficient ahead of Dry Run 2Steering Committee15 Jan 2027
D-003Adopt a dual-shore (onshore/offshore) QA model rather than onshore-only, ratified alongside CR-007Program Manager03 Sep 2026
D-004Engage an external firm for SOX compliance assessment rather than relying on internal audit alone, given program complexitySteering Committee29 Aug 2026