← Federal Suite BenefitConnect · Schedule & Resources

Resource-Loaded WBS

Download Word

This is the resource-loaded view of the Task Order's Work Breakdown Structure. Every work package carries its named effort and cost, every hour traces to a named person on the Resource Plan, and — because this is a federal task order — effort is split by contractual period: the 12-month Base Period and the 6-month Option Period are priced, funded and reported separately, so loading them as one undifferentiated pool would misrepresent the contract.

225
WBS line items
194
Loaded work packages
35
Named resources
351
Assignments
74,984
Total effort (h)
$6,960,000
Total labor

1. How this WBS is loaded

Each work package names one accountable owner plus any named contributors. The distinction is not cosmetic: on a task order where the Government surveils performance through the QASP, a package with three names and no single answerable owner is a package with no one to hold to the standard.

The loading is allocation-aware. Each person's hours come from their Resource Plan line, which already carries their FTE percentage — and on this Task Order those vary widely (100%, 80%, 75%, 60%, 50%, 25%). A resource at 50% FTE is loaded at 50% capacity, not quietly modelled as though they were full-time. Hours are then distributed across the packages they work on in proportion to package duration.

Cost is distributed, not recomputed. Blended rates in the Resource Plan are rounded for presentation (2,080 hours at $112.98 is $234,998.40, but the line reads $235,000). Recomputing cost from rate × hours would therefore drift from the contract by a few dollars per person and by thousands across the roster. Each person's stated cost is allocated instead, so the total ties to the penny.

2. Effort & cost by contractual period

PeriodDurationResourcesPackagesEffort (h)Labor cost
Base Period12 months3516466,144$5,750,000
Option Period6 months17308,840$1,210,000
Total18 months3519474,984$6,960,000

The Option Period is deliberately smaller and differently shaped: it covers post-launch stabilization, so it draws 17 of the 35 resources rather than the full team, and its packages sit in the cutover, stabilization and closeout phases. Several people carry a lower FTE in the Option Period than in the Base Period — the ramp-down is priced into the contract, and this view shows it rather than assuming a flat team.

3. Reconciliation

CheckValueResult
Base Period distributed effort / cost66,144 h / $5,750,000= Resource Plan Base total ✓
Option Period distributed effort / cost8,840 h / $1,210,000= Resource Plan Option total ✓
Combined74,984 h / $6,960,000= Task Order Budget labor, $0 variance ✓
Per-resource, per-period35 of 35each equals that person's roster line exactly ✓

These are assertions the generator evaluates, not totals typed into a table — it refuses to emit this page if any of them fails. The $0 variance shown in the Resource Plan's own reconciliation table is reproduced here from the opposite direction: that table compares plan to budget, this one rebuilds the plan from the work packages up.

4. Effort & cost by phase

WBSPhasePackagesEffort (h)Labor cost% of total
1Task Order Kickoff & Mobilization284,866$492,6127.1%
2Requirements & Solution Architecture468,934$789,97111.4%
3Development & Data Migration Build5035,017$3,017,10143.3%
3BDocumentation & Training Materials42,872$225,7003.2%
4Section 508 / VPAT Testing (CDRL A006)124,586$364,1065.2%
5ATO Security Assessment & Package (CDRL A007)145,930$518,9667.5%
6Data Migration Cutover (CDRL A009)153,971$346,0615.0%
7Stabilization Support (Option Period)198,205$1,140,02716.4%
8Task Order Closeout (CDRL A010)6603$65,4560.9%
Task Order total19474,984$6,960,000100.0%

5. Resource loading by person

ResourceRoleFTE %PeriodsHoursCostPackages
C. TyrrellTask Order PM100% / 100%Base+Option3,120$365,00018
H. IbrahimBack-End Developer100% / 50%Base+Option2,600$300,0005
S. LarsenBack-End Developer (Eligibility API)100% / 50%Base+Option2,600$300,0005
T. AbernathyISSO (ATO Package Owner)100% / 100%Base+Option3,120$295,00017
K. LindqvistSolutions Architect / Tech Lead100% / 50%Base+Option2,600$285,00017
E. MarstonFront-End Developer100% / 50%Base+Option2,600$280,0007
P. ManningQA Automation Engineer100% / 50%Base+Option2,600$276,0004
R. NakashimaFront-End Developer (Mobile Redesign)100% / 50%Base+Option2,600$275,0004
D. FerrisDeputy PM100% / 50%Base+Option2,600$260,00018
D. VasquezSecurity Engineer (API Integration Review)100% / 50%Base+Option2,600$250,0004
S. VanceDevOps / Cloud Engineer80% / 50%Base+Option2,184$245,00011
N. CastellanoQA Lead80% / 50%Base+Option2,184$230,0004
A. ByrneQA Tester (Manual/Regression)100% / 50%Base+Option2,600$215,00013
G. PetrovBack-End Developer100%Base only2,080$190,0004
P. OchiengData Migration Specialist (Eligibility Data)100%Base only2,080$190,0003
R. TalbotDatabase / ETL Engineer100%Base only2,080$190,0004
T. HallowayBack-End Developer (Eligibility API)100%Base only2,080$190,0004
N. BeaumontQA Automation Engineer100%Base only2,080$186,0003
A. BeaumontBack-End Developer100%Base only2,080$180,00015
Q. RedmondBack-End Developer100%Base only2,080$180,00015
R. ColvilleFront-End Developer100%Base only2,080$180,0004
J. WinfieldFront-End Developer (Mobile Redesign)100%Base only2,080$175,0002
L. AndersUX / Accessibility Designer100%Base only2,080$175,00030
V. PrescottFront-End Developer (Accessibility Remediation)100%Base only2,080$175,0005
R. FontenotBusiness Analyst (Eligibility API)100%Base only2,080$160,00023
A. BrennanDevOps / Cloud Engineer80%Base only1,664$150,0002
L. SorensonQA Tester (Manual)100%Base only2,080$140,0003
M. DelvecchioQA Tester (Manual)100%Base only2,080$140,0003
J. OkonkwoBusiness Analyst75%Base only1,560$120,00020
K. MarchettiBusiness Analyst (Mobile Redesign)75%Base only1,560$120,00014
B. HollowayRelease / Configuration Manager60% / 25%Base+Option1,508$115,0007
C. WhitworthSchedule / PMO Analyst60% / 25%Base+Option1,508$115,00041
K. AshworthCompliance / Privacy Analyst50% / 25%Base+Option1,300$105,0002
P. DuvallSection 508 / Accessibility Compliance Lead60%Base only1,248$105,00010
E. MarchandTechnical Writer / Documentation Specialist60% / 25%Base+Option1,508$103,00010
Total — 35 resources74,984$6,960,000351

6. Loaded work packages

All 194 loaded work packages with owner, contributors, period, effort and cost. Effort is carried at work-package level only, so nothing is double-counted in the rollups above.

WBSWork packageAccountable ownerContributorsPeriodEffort (h)Cost
1.1.1Contract kickoff meeting with COR/COC. TyrrellC. WhitworthBase175$19,201
1.1.2Issue offer letters — leadership roles (PM, Deputy PM, Architect, ISSO)D. FerrisBase109$10,789
1.1.3Issue offer letters — 508 Lead, QA Lead, BAD. FerrisL. AndersBase144$13,806
1.1.4Issue offer letters — Front-End Developers (2)D. FerrisBase109$10,789
1.1.5Issue offer letters — Back-End Developers (2)D. FerrisA. Beaumont, Q. RedmondBase207$19,359
1.1.6Issue offer letters — DevOps Engineer & QA TesterD. FerrisBase109$10,789
1.1.7Badge/facility access provisioningD. FerrisBase227$21,587
1.1.8System/network access provisioning — dev teamS. VanceBase175$15,789
1.1.9New-hire security briefing (PHI/PII handling)T. AbernathyBase54$5,064
1.1.10New-hire Section 508 awareness briefingP. DuvallL. AndersBase89$7,582
1.1.11Tooling/license procurement — IDE, design, ticketingD. FerrisL. AndersBase289$27,612
1.1.12Establish team communication channels & shared drivesD. FerrisBase109$10,789
1.2.1Draft Project Management Plan outlineC. TyrrellC. WhitworthBase175$19,201
1.2.2PM Plan — scope & schedule management sectionsC. TyrrellC. WhitworthBase175$19,201
1.2.3PM Plan — cost & quality management sectionsD. FerrisC. WhitworthBase124$11,914
1.2.4PM Plan — risk & communications management sectionsC. TyrrellC. WhitworthBase175$19,201
1.2.5PM Plan — staffing & change management sectionsD. FerrisC. WhitworthBase124$11,914
1.2.6PM Plan internal reviewD. FerrisC. WhitworthBase124$11,914
1.2.7Submit PM Plan (CDRL A001) to CORC. TyrrellC. WhitworthBase175$19,201
1.2.8Draft IMS baseline — Base Period milestonesD. FerrisC. WhitworthBase249$23,828
1.2.9Draft IMS baseline — Option Period milestonesD. FerrisC. WhitworthBase124$11,914
1.2.10IMS baseline internal reviewC. TyrrellC. WhitworthBase175$19,201
1.2.11Submit IMS (CDRL A002) to CORD. FerrisC. WhitworthBase124$11,914
1.3.1Draft Communications PlanD. FerrisC. WhitworthBase249$23,828
1.3.2Establish weekly delivery standup cadenceC. TyrrellBase160$18,076
1.3.3Establish bi-weekly COR sync cadenceC. TyrrellBase160$18,076
1.3.4Establish Quality Review Board cadenceN. CastellanoBase277$25,833
1.3.5Draft RAIDD Log & initial risk identification workshopC. TyrrellBase480$54,240
2.1.1Stakeholder interview — COR & FOPBA Program OfficeJ. OkonkwoBase67$5,217
2.1.2Stakeholder interview — Sponsor & mission ownerJ. OkonkwoBase67$5,217
2.1.3Stakeholder interview — end applicants (representative panel)J. OkonkwoBase151$10,443
2.1.4Stakeholder interview — 508/accessibility advocacy reviewersJ. OkonkwoL. AndersBase102$8,234
2.1.5Stakeholder interview — legacy platform SMEsJ. OkonkwoBase67$5,217
2.1.5BStakeholder interview — help desk / call center staffJ. OkonkwoBase67$5,217
2.1.6Draft functional requirements — account & identityJ. OkonkwoK. Marchetti, R. FontenotBase202$15,692
2.1.6BDraft functional requirements — MFA/identity-assuranceJ. OkonkwoK. Marchetti, R. FontenotBase202$15,692
2.1.7Draft functional requirements — benefits application intakeJ. OkonkwoK. Marchetti, R. FontenotBase202$15,692
2.1.7BDraft functional requirements — eligibility pre-screeningJ. OkonkwoA. Beaumont, K. Marchetti, Q. Redmond, R. FontenotBase300$24,262
2.1.8Draft functional requirements — status tracking & document uploadJ. OkonkwoC. Whitworth, K. Marchetti, R. FontenotBase217$16,817
2.1.8BDraft functional requirements — document format & size validationJ. OkonkwoK. Marchetti, R. FontenotBase202$15,692
2.1.9Draft functional requirements — notifications & remindersJ. OkonkwoK. Marchetti, R. FontenotBase202$15,692
2.1.9BDraft functional requirements — help desk/call-center handoffJ. OkonkwoK. Marchetti, R. FontenotBase202$15,692
2.1.10Draft non-functional requirements — security & privacyJ. OkonkwoK. Marchetti, R. FontenotBase202$15,692
2.1.11Draft non-functional requirements — performance & availabilityJ. OkonkwoK. Marchetti, R. FontenotBase202$15,692
2.1.12Draft non-functional requirements — accessibility (508/WCAG)J. OkonkwoK. Marchetti, L. Anders, R. FontenotBase237$18,709
2.1.13Requirements traceability matrix — buildJ. OkonkwoK. Marchetti, R. FontenotBase407$31,386
2.1.14Requirements sign-off with CORJ. OkonkwoK. Marchetti, R. FontenotBase407$31,386
2.2.1Application architecture — front-end framework selectionK. LindqvistBase184$20,000
2.2.2Application architecture — back-end/API framework selectionK. LindqvistA. Beaumont, Q. Redmond, R. FontenotBase481$44,761
2.2.3Application architecture — front-end/back-end integration designK. LindqvistA. Beaumont, L. Anders, Q. RedmondBase225$21,587
2.2.4Architecture Decision Records — framework & platform choicesK. LindqvistBase184$20,000
2.2.5Data architecture — schema design for applicant recordsK. LindqvistL. AndersBase255$26,034
2.2.6Data architecture — legacy integration/extraction designK. LindqvistL. AndersBase393$39,051
2.2.7Data architecture — retention & archival designK. LindqvistL. AndersBase127$13,017
2.2.8Security architecture — identity & MFA designK. LindqvistL. AndersBase255$26,034
2.2.9Security architecture — encryption at rest & in transitK. LindqvistBase92$10,000
2.2.10Security architecture — network segmentation & boundary protectionK. LindqvistBase92$10,000
2.2.11Threat modeling workshop (STRIDE walkthrough)T. AbernathyBase108$10,129
2.3.1ARB pre-read package assembly (ADRs, diagrams, threat model)K. LindqvistBase184$20,000
2.3.2ARB internal walkthrough — application & data architectureK. LindqvistBase92$10,000
2.3.3ARB internal walkthrough — security architecture & threat modelT. AbernathyBase54$5,064
2.3.4ARB findings remediation (design revisions)K. LindqvistL. AndersBase127$13,017
2.3.5ARB COR briefing & sign-offK. LindqvistBase92$10,000
2.3.6Milestone Gate: Architecture Approved for BuildK. LindqvistBase46$5,000
2.4.1ATO-compliant cloud landing zone — network setupS. VanceBase175$15,789
2.4.2ATO-compliant cloud landing zone — IAM & least-privilege rolesS. VanceBase175$15,789
2.4.3ATO-compliant cloud landing zone — logging & monitoring baselineS. VanceC. WhitworthBase102$9,019
2.4.4CI/CD pipeline scaffolding — build stageS. VanceBase87$7,894
2.4.5CI/CD pipeline scaffolding — automated test/security-scan stageS. VanceBase175$15,789
2.4.6Section 508 Test Plan (CDRL A004) — draftP. DuvallC. Whitworth, L. AndersBase210$17,414
2.4.7Section 508 Test Plan (CDRL A004) — submit to CORP. DuvallC. Whitworth, L. AndersBase210$17,414
2.4.8UI/UX wireframes — account & login flowsE. MarstonL. AndersBase368$33,176
2.4.9UI/UX wireframes — application intake flowE. MarstonL. AndersBase368$33,176
2.4.10UI/UX design system — component library specE. MarstonL. AndersBase368$33,176
3.1.1Component library — buttons & form controlsR. NakashimaBase892$79,286
3.1.2Component library — accessible form controls (508)J. WinfieldL. AndersBase887$74,676
3.1.3Component library — navigation & layout shellE. MarstonBase297$27,142
3.1.4Component library — data tables & status indicatorsR. NakashimaC. WhitworthBase625$55,107
3.2.1Citizen portal UI — account creation flowV. PrescottBase346$29,166
3.2.2Citizen portal UI — login & MFA flowR. ColvilleBase462$40,000
3.2.3Citizen portal UI — password reset flowV. PrescottBase346$29,166
3.2.4Citizen portal UI — benefits application form (part 1 of 2)R. ColvilleBase462$40,000
3.2.5Citizen portal UI — benefits application form (part 2 of 2)V. PrescottBase346$29,166
3.3.1Citizen portal UI — document upload flowR. ColvilleBase694$60,000
3.3.2Citizen portal UI — application status trackerV. PrescottC. WhitworthBase568$47,127
3.3.3Front-end code review — Sprints A-CE. MarstonBase297$27,142
3.3.4Front-end accessibility self-check pass (pre-508-audit)R. NakashimaL. AndersBase665$58,891
3.4Front-end unit testing — full regressionJ. WinfieldBase1,300$109,375
3.4B.1Front-end — notification preference center UIV. PrescottBase520$43,750
3.4B.2Front-end — in-app notification banner componentR. ColvilleBase462$40,000
3.4B.3Back-end — notification scheduling serviceH. IbrahimA. Beaumont, C. Whitworth, Q. RedmondBase670$60,667
3.4B.4Back-end — email/SMS delivery integrationH. IbrahimA. Beaumont, Q. RedmondBase624$57,292
3.4B.5Notification feature test passA. ByrneBase892$60,000
3.5.1Core API — account & identity endpointsS. LarsenA. Beaumont, Q. Redmond, R. FontenotBase1,526$138,419
3.5.2Core API — application intake endpointsT. HallowayA. Beaumont, Q. Redmond, R. FontenotBase1,289$112,857
3.5.3Core API — document storage endpointsH. IbrahimA. Beaumont, Q. Redmond, R. FontenotBase772$68,720
3.5.4Core API — status/notification endpointsS. LarsenA. Beaumont, C. Whitworth, Q. Redmond, R. FontenotBase790$71,455
3.5.5Core API — MFA/identity-assurance integration (Mod P00004)T. HallowayA. Beaumont, Q. Redmond, R. FontenotBase643$56,427
3.6.1Back-end code review — API layerS. LarsenA. Beaumont, Q. Redmond, R. FontenotBase759$69,205
3.6.2Core API unit & integration testingT. HallowayA. Beaumont, Q. Redmond, R. FontenotBase643$56,427
3.7.1Legacy data extraction tooling — applicant recordsP. OchiengBase1,040$95,000
3.7.2Legacy data extraction tooling — in-flight application recordsR. TalbotBase624$57,000
3.7.3Legacy data extraction tooling — document archiveG. PetrovBase624$57,000
3.8.1Data transformation & mapping pipeline — schema mappingR. TalbotBase832$76,000
3.8.2Data transformation & mapping pipeline — validation rulesG. PetrovR. FontenotBase1,030$91,238
3.8.3Reduced-scope tooling savings review (Mod P00007)G. PetrovBase416$38,000
3.9Back-end integration testing — full regressionH. IbrahimA. Beaumont, Q. RedmondBase2,094$190,994
3.10.1System Security Plan — system boundary & inventoryT. AbernathyC. WhitworthBase348$30,949
3.10.2System Security Plan — control implementation narrativeT. AbernathyC. WhitworthBase573$49,532
3.10.3System Security Plan — SSP (CDRL A005) submissionT. AbernathyC. WhitworthBase139$12,379
3.10.4Disaster Recovery / COOP test plan (Mod P00008)S. VanceC. WhitworthBase518$45,103
3.11.1Functional test case development — account/identityP. ManningBase624$55,800
3.11.2Functional test case development — application intakeN. CastellanoBase833$77,501
3.11.3Functional test case development — document & status flowsP. ManningC. WhitworthBase894$78,900
3.11.4Functional test execution — account/identityL. SorensonBase780$52,500
3.11.5Functional test execution — application intakeM. DelvecchioBase925$62,223
3.11.6Functional test execution — document & status flowsN. BeaumontC. WhitworthBase1,071$95,250
3.12.1Load test scenario design (peak enrollment period)S. VanceL. AndersBase246$21,823
3.12.2Load test execution — API layerA. BrennanA. Beaumont, Q. Redmond, R. FontenotBase962$84,761
3.12.3Load test execution — front-end under concurrent loadS. VanceBase175$15,789
3.12.4Performance tuning based on load test findingsS. LarsenBase231$22,222
3.13.1Desktop browser compatibility pass (Chrome, Edge, Firefox, Safari)L. SorensonBase780$52,500
3.13.2Mobile browser compatibility pass (iOS Safari, Android Chrome)M. DelvecchioK. MarchettiBase961$66,674
3.13.3Screen-reader compatibility spot-check (pre-VPAT)N. BeaumontBase520$46,500
3B.1Applicant user guide — account & application flowE. MarchandBase749$46,800
3B.2Applicant user guide — accessibility features overviewE. MarchandL. AndersBase570$37,234
3B.3COR/Program Office admin runbook — system operationsA. BrennanBase999$90,000
3B.4Help desk support script & FAQ (reduces post-launch tickets)N. CastellanoBase554$51,666
4.1Automated accessibility regression tool licensing & setup (Mod P00006)A. ByrneL. AndersBase665$46,034
4.2Automated accessibility regression testing — account/identityL. SorensonL. AndersBase591$41,034
4.3Automated accessibility regression testing — application flowsM. DelvecchioL. AndersBase533$37,145
4.4Automated accessibility regression testing — document/status flowsN. BeaumontC. Whitworth, L. AndersBase570$50,642
4.5Manual VPAT testing — screen reader compatibilityP. DuvallBase162$13,695
4.6Manual VPAT testing — keyboard navigation & focus orderP. DuvallBase162$13,695
4.7Manual VPAT testing — color contrast & text scalingP. DuvallL. AndersBase179$15,164
4.8Independent 508 audit — vendor onboarding (Mod P00001)P. DuvallL. AndersBase179$15,164
4.9Independent 508 audit — findings reviewP. DuvallL. AndersBase179$15,164
4.10Independent 508 audit remediation — component fixesE. MarstonL. AndersBase760$66,372
4.11Independent 508 audit — re-verificationP. DuvallL. AndersBase179$15,164
4.12Section 508 Test Report (CDRL A006) — draft & submitP. DuvallC. Whitworth, L. AndersBase427$34,833
5.1Security Assessment Report — automated vulnerability scanningT. AbernathyC. WhitworthBase139$12,379
5.2Security Assessment Report — manual configuration reviewT. AbernathyB. Holloway, C. WhitworthBase971$72,379
5.3Security Assessment Report — penetration test scopingD. VasquezC. WhitworthBase863$82,250
5.4Security Assessment Report — penetration test execution (3rd party)D. VasquezC. WhitworthBase1,294$123,375
5.5Security Assessment Report — findings triage & severity ratingT. AbernathyC. WhitworthBase139$12,379
5.6Security Assessment Report — findings documentationT. AbernathyC. WhitworthBase139$12,379
5.7Security Assessment Report — draft & internal reviewT. AbernathyC. WhitworthBase139$12,379
5.8POA&M development — open findings prioritizationT. AbernathyBase108$10,129
5.9POA&M development — remediation timeline & ownersK. AshworthBase1,040$80,000
5.10POA&M development — critical finding remediation (pre-ATO)T. HallowayBase693$63,333
5.11ATO package assembly (SSP + SAR + POA&M)T. AbernathyBase162$15,194
5.12ATO package submission (CDRL A007)T. AbernathyBase54$5,064
5.13ATO authorization bridge extension (Mod P00005)T. AbernathyBase162$15,194
5.14Milestone Gate: ATO GrantedT. AbernathyBase27$2,532
6.1Data migration validation — record-count reconciliationP. OchiengBase520$47,500
6.2Data migration validation — field-level accuracy samplingR. TalbotBase416$38,000
6.3Data migration validation — orphaned-record detectionG. PetrovBase208$19,000
6.4Data migration validation report (CDRL A009) — draftP. OchiengC. WhitworthBase551$49,750
6.5Data migration validation report (CDRL A009) — submit to CORR. TalbotC. WhitworthBase223$20,125
6.6Full regression test suite — automatedP. ManningBase624$55,800
6.7Full regression test suite — manual exploratoryA. ByrneBase594$40,000
6.8Production Readiness Review — go-live checklist walkthroughC. TyrrellBase160$18,076
6.9Production Readiness Review — COR/Sponsor briefingC. TyrrellBase160$18,076
6.10Cutover communications — applicant notice of maintenance windowJ. OkonkwoB. HollowayBase483$35,217
6.11Cutover rehearsal (dry run)A. BrennanB. HollowayOption2$234
6.12Cutover execution — DNS/traffic cutoverS. VanceB. HollowayOption6$1,121
6.13Cutover execution — legacy platform read-only lockdownA. BrennanB. Holloway, D. VasquezOption6$701
6.14Post-cutover smoke testL. SorensonA. Byrne, B. HollowayOption3$492
6.15Milestone Gate: Production Go-LiveC. TyrrellOption15$1,969
7.1.1Front-end defect-fix sustainment — Month 1-2J. WinfieldA. ByrneOption37$5,421
7.1.2Front-end defect-fix sustainment — Month 3-4E. MarstonA. ByrneOption557$95,421
7.1.3Front-end defect-fix sustainment — Month 5-6R. NakashimaA. ByrneOption555$95,163
7.1.4Back-end defect-fix sustainment — Month 1-2H. IbrahimA. ByrneOption557$105,421
7.1.5Back-end defect-fix sustainment — Month 3-4S. LarsenA. ByrneOption557$105,421
7.1.6Back-end defect-fix sustainment — Month 5-6T. HallowayA. ByrneOption35$5,163
7.2Continuous ATO monitoring & POA&M closure trackingT. AbernathyD. Vasquez, K. AshworthOption1,816$174,533
7.3.1Regression support testing — monthly pass, Q1P. ManningA. ByrneOption576$98,132
7.3.2Regression support testing — monthly pass, Q2N. CastellanoA. ByrneOption576$83,132
7.3.3Release verification testing — ongoingM. DelvecchioA. Byrne, B. HollowayOption441$50,532
7.4Infrastructure sustainment & cost optimizationS. VanceOption516$94,113
7.5.1Status Report — Option Month 1C. WhitworthE. MarchandOption132$12,400
7.5.2Status Report — Option Month 2C. TyrrellE. MarchandOption360$43,463
7.5.3Status Report — Option Month 3C. WhitworthE. MarchandOption128$12,398
7.5.4Status Report — Option Month 4C. TyrrellE. MarchandOption357$43,458
7.5.5Status Report — Option Month 5C. WhitworthE. MarchandOption128$12,398
7.5.6Status Report — Option Month 6C. TyrrellE. MarchandOption357$43,458
7.6Quarterly Architecture Review — post-launch drift checkK. LindqvistOption260$30,000
7.7Quarterly Architecture Review — Option Period midpointK. LindqvistOption260$30,000
8.1Final CDRL reconciliation & acceptance reviewD. FerrisOption260$27,500
8.2Final contract modification reconciliationD. FerrisOption130$13,750
8.3Closeout Report — draftC. TyrrellE. MarchandOption35$4,345
8.4Lessons Learned Register — compile & finalizeC. TyrrellOption31$3,939
8.5CDRL Closeout Certification — submit to CORD. FerrisE. MarchandOption132$13,953
8.6Milestone: Task Order ClosedC. TyrrellOption15$1,969