← AI Transformation Suite Financial Controls · Budget Baseline

Program Budget

Download Word

The authorized cost baseline for Project Catalyst — $99,000,000 over 36.5 months. This document is the single financial control point for the program: it presents the baseline three ways (by cost category, by contract year, by WBS workstream), sets out the quarterly spend plan and earned-value baseline against which performance is measured, and records the rate card, funding schedule, contingency ledger, and the assumptions the numbers rest on. Status date: 11 September 2026 (Week 4, Phase 0).

Authorized Baseline
$99.0M
BAC · unchanged
Spent to Date
$2.0M
2.0% of BAC
Cost Performance
CPI 1.00
$0 variance
Contingency
$9.0M
9.1% · undrawn
Forecast at Completion
$99.0M
EAC · VAC $0
Baseline status: stable. The cost baseline has not changed since Charter authorization on 17 August 2026. No change request has altered the total authorized amount, no contingency has been released, and cost and schedule performance indices both sit at 1.00 at the Week-4 status date.

1 · Baseline by Cost Category

The Charter §13.1 cost structure. Labor accounts for $61.2M (61.8%) across three staffing models; cloud and AI platform infrastructure is the single largest non-labor line, reflecting a program whose core deliverable is a production AI platform.

Cost CategoryBasisAmount% of Total
Internal FTE Labor (ACME)Loaded cost of ACME staff assigned to the program$19,600,00019.8%
Onshore Consultant Labor (Pulaski)Billable onshore consulting staff at contracted rates$27,400,00027.7%
Offshore Consultant Labor (Pulaski)Billable offshore engineering and QA capacity$14,200,00014.3%
Labor subtotal$61,200,00061.8%
Cloud & AI Platform InfrastructureHyperscaler compute/storage, GenAI inference, MLOps tooling$26,900,00027.2%
Tooling & LicensesDelivery tooling, QA/test automation, observability$1,900,0001.9%
Contingency ReserveESB-controlled, released against realized risk$9,000,0009.1%
Total Authorized Budget$99,000,000100.0%

2 · Baseline by Contract Year (SOW Envelopes)

Each program year is contracted under a separate Statement of Work. Year 2 is the peak spend year, when BRD-02 and BRD-03 are delivered in parallel at maximum concurrent staffing.

YearPeriodScope FocusEnvelope% of Total
Year 1Aug 2026 – Aug 2027Foundation, CoE & governance, platform build, BRD-01 to production$27,720,00028.0%
Year 2Sep 2027 – Aug 2028BRD-02 and BRD-03 parallel delivery (peak staffing)$41,580,00042.0%
Year 3Sep 2028 – Aug 2029Optimization, benefits realization, transition & closeout$29,700,00030.0%
Total36.5 months$99,000,000100.0%

Envelopes tie exactly to SOW-01, SOW-02 and SOW-03 and to the investment schedule in the Cost-Benefit Analysis.

3 · Baseline by WBS Workstream

The same $99.0M allocated against the seven WBS elements — the view used for work-package cost control on the WBS Budget Rollup.

WBSWorkstreamTypeBudget% of Total
1.0Program Management & PMOManagement$12,600,00012.7%
2.0Data & Cloud AI PlatformCross-cutting$20,700,00020.9%
3.0AI Governance & Center of ExcellenceCross-cutting$13,200,00013.3%
4.0BRD-01 · Claims & Prior Authorization AIDelivery$11,020,00011.1%
5.0BRD-02 · Member & Provider Experience AIDelivery$13,200,00013.3%
6.0BRD-03 · Underwriting & Risk AIDelivery$12,480,00012.6%
7.0Optimization, Benefits & CloseoutSustain$15,800,00016.0%
Total$99,000,000100.0%
Three views, one number. Category, contract year, and workstream are three cuts of the same authorized $99.0M — each foots to the total exactly. Any approved change request must be reflected in all three views simultaneously, and the Change Control Log is the controlling record.

4 · Quarterly Spend Plan & Cash-Flow Curve

Planned expenditure by program quarter. The curve shows the expected S-shape: a deliberately slow Phase-0 mobilization, steep ramp through BRD-01 delivery, a Year-2 plateau at peak concurrent staffing, then a Year-3 taper as delivery teams roll off and the program transitions to steady-state operations.

Y1Q1
Y1Q2
Y1Q3
Y1Q4
Y2Q1
Y2Q2
Y2Q3
Y2Q4
Y3Q1
Y3Q2
Y3Q3
Y3Q4
Quarterly spend    Cumulative % of $99.0M baseline
QuarterPeriodPhase FocusPlanned SpendCumulativeCum. %
Y1 Q1Aug – Nov 2026Phase 0 mobilization, readiness, vendor selection$4,200,000$4,200,0004.2%
Y1 Q2Dec 2026 – Feb 2027BRD-01 requirements, platform foundation build$6,300,000$10,500,00010.6%
Y1 Q3Mar – May 2027Platform live, BRD-01 model development$8,100,000$18,600,00018.8%
Y1 Q4Jun – Aug 2027BRD-01 test, IMV, UAT, production go-live$9,120,000$27,720,00028.0%
Year 1$27,720,000
Y2 Q1Sep – Nov 2027BRD-02 & BRD-03 mobilization and design$9,500,000$37,220,00037.6%
Y2 Q2Dec 2027 – Feb 2028Parallel build — peak staffing$10,800,000$48,020,00048.5%
Y2 Q3Mar – May 2028Parallel build & test — peak spend$11,000,000$59,020,00059.6%
Y2 Q4Jun – Aug 2028BRD-02 UAT and production preparation$10,280,000$69,300,00070.0%
Year 2$41,580,000
Y3 Q1Sep – Nov 2028BRD-02 production, BRD-03 validation & go-live$9,600,000$78,900,00079.7%
Y3 Q2Dec 2028 – Feb 2029Optimization and retraining cycles$8,400,000$87,300,00088.2%
Y3 Q3Mar – May 2029Benefits audit, knowledge transfer$6,900,000$94,200,00095.2%
Y3 Q4Jun – Aug 2029Steady-state transition and closeout$4,800,000$99,000,000100.0%
Year 3$29,700,000
Total$99,000,000$99,000,000100.0%

5 · Earned Value Baseline

The spend plan above is the performance measurement baseline (PMB) against which earned value is calculated. Position at the 11 September 2026 status date:

MeasureDefinitionValueInterpretation
BAC — Budget at CompletionTotal authorized baseline$99,000,000Unchanged since authorization
PV — Planned ValueBudgeted cost of work scheduled to date$2,000,000Week-4 Phase-0 position
EV — Earned ValueBudgeted cost of work performed$2,000,000Work performed matches plan
AC — Actual CostActual cost of work performed$2,000,000Spend matches earned value
SV — Schedule Variance (EV−PV)Schedule position in cost terms$0On schedule
CV — Cost Variance (EV−AC)Cost position$0On budget
SPI — Schedule Performance IndexEV ÷ PV1.00On baseline
CPI — Cost Performance IndexEV ÷ AC1.00On baseline
EAC — Estimate at CompletionBAC ÷ CPI$99,000,000Forecast equals baseline
ETC — Estimate to CompleteEAC − AC$97,000,000Remaining forecast spend
VAC — Variance at CompletionBAC − EAC$0No forecast overrun

Budget-weighted completion is 2.0% (EV ÷ BAC). The Resource-Loaded WBS reports schedule (duration-weighted) percent complete for the same status date — a different, complementary measure. EVM is reported monthly to the Executive Steering Board by Program Finance.

6 · Cost by Phase

PhasePeriodBudget% of TotalPrincipal Cost Drivers
Phase 0 — Foundation & MobilizationAug – Nov 2026$4,200,0004.2%Readiness assessment, governance stand-up, vendor selection
Phase 1 — BRD-01 DeliveryDec 2026 – Aug 2027$23,520,00023.8%Platform foundation, BRD-01 build/test/IMV, first production go-live
Phase 2 — Expansion (BRD-02 & BRD-03)Sep 2027 – Aug 2028$41,580,00042.0%Peak concurrent staffing, parallel delivery, scaled compute
Phase 3 — Optimization & CloseoutSep 2028 – Aug 2029$29,700,00030.0%Retraining, benefits audit, knowledge transfer, transition
Total$99,000,000100.0%

7 · Labor Rate Card

Blended rate structure underpinning the $61.2M labor baseline, drawn from the Resource Plan. Onshore-only staffing is contractually required for Legal, Compliance, SOX, executive, and PHI claims-decision roles; offshore capacity is concentrated in platform engineering and QA.

Staffing ModelRoles CoveredHeadcountRate RangeBlended
ACME Internal FTE (onshore)Executive, business SME, clinical, operations, UAT, IT operations132$62 – $280/hr$135/hr
Pulaski Consultant — onshoreProgram leadership, architecture, AI/ML engineering, governance, IMV75$90 – $165/hr$133/hr
Pulaski Consultant — offshorePlatform & data engineering, QA and test automation55$60 – $85/hr$74/hr
Life-of-program roster262$60 – $280/hr$122/hr

Headcount is the life-of-program roster, not concurrent staffing; teams ramp on and off by phase. Rates are held firm for the life of each annual SOW, with escalation negotiated at renewal (see assumptions below).

8 · Funding & Authorization Schedule

Funding is authorized annually against SOW execution, not released as a single lump sum. Each authorization is contingent on the prior year's phase-gate outcome, giving the Executive Steering Board a genuine stage-gate on continued investment.

AuthorizationTriggerAmountStatus
Year 1 funding (SOW-01)Charter approval & SOW-01 execution$27,720,000Authorized 17 Aug 2026
Year 2 funding (SOW-02)Year-1 close & BRD-01 production acceptance$41,580,000Planned Sep 2027
Year 3 funding (SOW-03)Year-2 close & BRD-02/03 delivery acceptance$29,700,000Planned Sep 2028
Total program authorization$99,000,000

Invoicing runs against milestone payment schedules defined in each SOW; Program Finance reconciles invoices to earned value monthly, and SOX/Financial Controls reviews any item affecting claims-payment or financial-reporting systems.

9 · Contingency Reserve Ledger

The $9.0M contingency (9.1% of baseline) is held by the Executive Steering Board and released only against realized risk, never to absorb scope growth — scope changes follow the change-control path and require their own funding decision.

DateEventLinked RiskDrawnBalance
17 Aug 2026Contingency established at Charter authorization$0$9,000,000
11 Sep 2026Position at status date — no drawdowns to date$0$9,000,000

Release authority

Drawdown AmountApproval AuthorityEvidence Required
Up to $250,000Program DirectorRAIDD entry, cost basis, PMO log
$250,000 – $500,000Program Director + Program FinanceRoot cause, alternatives considered
$500,000 – $1,000,000Executive Steering BoardFormal presentation with root cause, alternatives, payback
Above $1,000,000Executive Sponsor (direct approval)Full business case and re-baselining assessment
Reserve adequacy. The ten anticipated risks on the RAIDD Log were sized against this reserve at authorization. The two largest exposures — legacy data remediation (RSK-01) and GenAI compute cost escalation (RSK-02) — are together the primary reason the reserve is set at 9.1% rather than a more typical 5–7% for an IT program of this size.

10 · Budget Assumptions & Exclusions

Assumptions

Exclusions

11 · Budget Controls & Reporting

ControlCadenceOwnerEscalation
EVM calculation & variance analysisMonthlyProgram Finance (A. Rodriguez)CPI or SPI < 0.95 → ESB
Actuals-to-invoice reconciliationMonthlyProgram FinanceVariance > 2% → Program Director
Forecast (EAC) refreshQuarterlyProgram Finance + PMOVAC > $1M → ESB
Cloud/AI compute cost review (FinOps)MonthlyPlatform Lead + Program FinanceRun-rate breach → EARB & ESB
Contingency ledger reviewMonthlyPMO (T. Valdez)Per release-authority table above
SOX controls testing (payment-affecting scope)Per releaseSOX / Financial ControlsControl failure → Compliance & ESB
Reading this document. The budget is the cost baseline; the CBA tests whether that investment is worth making, the TCO extends the view to ten-year ownership, and the WBS Budget Rollup decomposes it to work-package level for day-to-day control. Approved changes flow through the Change Control Log.